Thailand Construction: Bangkok Builder’s New House Build is 3 weeks ahead of Schedule

The construction of the house for our client at Prachinburi, continues to go very well. Currently 3 weeks ahead of schedule. Ground slab works are completed and moving ahead with preparation on the 1st floor column work. All steel rebar is on site.

As a professional construction contractor in Thailand, we check all steel and concrete to make sure it is to the best specification possible and according to all technical detail in the architect’s construction drawings. All stages of construction are checked by our construction consultant, supervised by our project manager and foreman. Our goal is to always carry out the construction to the very best possible levels of quality and standards we can. Clients are welcome to check the building progress and contact us any time. If you are looking for the professional construction contractor please do not hesitate to contact us. We love building and construction. So it is a pleasure to act as your chosen house builder. We also are finishing the construction of a large factory too. So we able to provide residential construction, as well as commercial construction.

Ground Slab Work – Concrete Pour For Customers House Construction in Prachinburi

Here is the latest update for our customers house construction in Prachinburi, Thailand. We are happy to say the ground slab concrete pour is happening today. The customer is very happy, as we are now 3 weeks ahead of schedule. Bangkok Builder always tries to keep to the schedule provided, or if we can, be ahead of the schedule. Much depends on when one starts a construction project with regards to the seasons, which effect works. If there is very heavy rain, then this naturally slows progress. So it is a good diea to start a construction project at the right times. Currently the weather is dry and fine, as we started the house build in the dry season. Thank you for showing interest in Bangkok Builder’s updates and the construction project. We have a page which provides further information on building your house in Thailand with us.

Save

Save

Save

Save

Save

Save

House Construction in Thailand – Bangkok Builder

Bangkok Construction Contractor: Bangkok Builder Can Help
Building a house in Thailand can be an enjoyable proposition and you can result in you having a wonderful home. But careful consideration must be given to how long it takes, the correct steps and working with a professional construction contractor.

The two main parts are the architectural design stage and then the construction stage. Bangkok builders can provide both or part of this. If you have architectural drawings completed by a licenced Thai architect and Thai engineer, we can provide you a quotation to build your house. If you do not have architectural drawings, we can also offer this service too. We have our own English speaking Thai architects who have assisted many people like you, design their home.
To design and build a house in Thailand, you are looking realistically at a minimum of 12-18 months, maybe more. This is determined by various factors, including the size and complexity of the house and how quickly the design comes together. An average size house in Thailand will take up to 12 months to build. Smaller houses maybe are able to be constructed in 10 months. All of this can be discussed and confirmed when you contact us at www.bangkokbuilder.com

Bangkok Builder Latest News: Ground Beam Completed, Termite Spraying and System Installed at Customers New House in Prachinburi

Some of the latest update photographs of our new house construction project in Prachinburi. The Ground beam is completed. We have now sprayed for termites and installed the termite system to enable the client to have the termite service every few months. The main pipes for water and drainage has also started. Thank you to all the Bangkok build team for their hard work on building the house.

Bangkok Builders Construction of a Luxury Home at Lakewood Golf Club, Bangkok

Bangkok Builder was pleased to have completed the construction of a luxury, Thai house, for a client at Lakewood Golf Club, Bangkok. We worked closely with our architect and the client to design the property. Once it was all completed, as the chosen house builder, we then started the construction of the house. The home used some natural stone, sand stone and German standard wooden flooring. It had a main swimming pool and child’s pool, separated by a bridge, which went over to the Sala. There was also an individual heated Jacuzzi.  Our smart home systems expert installed automated lighting systems, automatic remote control gates and various smart home systems for the client.

The house was built with 6 bedrooms, 7 bathrooms, living room/dining room, modern luxury kitchen, office/library, storage room, laundry room, maids accommodation, Thai kitchen and carport for 3 cars.  The master bedroom suite had a glass shower cubicle, with three types of showers, with a wall in a natural stone finish. There was also an external outside rain shower. Our carpenters installed and built walk in wardrobes and dressing room.

Another main feature in the master bedroom, was a custom made, in ground heated spa bath, with exact temperature control and automated refill. It was in fact the first time a spa bath of this size, which filled in an incredibly fast amount of time, had ever been done in Thailand.  It was custom made for the client and the actual system too was specially created for the project. Special thanks to Pooltech who assisted with all technical details. Over head fans and air conditioning was used to keep the home cool, with plenty of good insulation in the roof.

The construction of this house in Bangkok, is an example of what we can do at Bangkok Builders, as a professional construction contractor. We love to build houses for clients, we love to design them and it is our primary goal to always finish with a happy customer. Building a house in Thailand, can be difficult if you do not know a professional construction contractor, so Bangkok Builder is here to assist you every step of the way. We have our own English speaking, experienced Thai architect, if you require architectural drawings and also offer the house building service too. If you already have architectural construction drawings, then we can provide a quotation for the construction of the house only. If you are looking to build a house in Bangkok, please do contact us.  We look forward to hearing from you.

 

Factory Construction in Rayong, Thailand

Our construction team build houses in Thailand, but we also do commercial construction projects too. Here are the latest photographs of the construction of an 8,000 sq.m factory, with office, retaining wall, fence, roads, parking and warehousing for Parawood (Rubber tree wood), in Rayong, Thailand. Total project size 20,000 sq.m. The construction of the factory is on time and will be completed in 3 months. Bangkok Builder can carry out factory construction and the construction of condominiums too. If you have to build a factory, or require a construction contractor to assist with the construction of a building, please do not hesitate to contact us.

House Construction (Piles, Footings, 3 Phase Electric & Inspections) For Our Customers New Home in Prachinburi

Bangkok Builder is very happy to say, we are two weeks ahead of schedule on the construction of a new, two story, 640 sq.m house in Prachinburi. Piles, footings, pile cut off, steel re-bar and ground beam ready for concrete pouring. All completed. Installation by PEA for 3 phase electricity completed. We only use quality materials with concrete and steel certification. We also do inspections of each stage of works and quality checks of materials. Inspections of center, dimension and height of footings, steel rebar and concrete test. We have our professional construction consultant of over 25 years of experience, inspect regularly on every project. We build homes in Bangkok, but also in neighboring provinces too. Please do not hesitate to contact Bangkok Builder anytime for help with the construction of your home in Prachinburi, Bangkok or neighboring provinces of Bangkok.

House Build Survey Completed For New Customers House Build, by Bangkok Builder

Boundary checks completed. Workers camp completed with private washing and toilet facilities. Land site survey and the arrival of the piles. The construction work begins ! As a house builder and construction contractor, we are always excited by a new construction project. It is really gratifying to build a house for a client. When the piling starts it is all steam ahead. The depth of how far a pile goes down into the ground, is calculated by the engineer, based on the engineering drawings/calculations and also the information he receives from the soil survey report. A soil survey is an important survey to have done, on any construction project. The soil survey team will go to the land and bore down, taking samples at various depths. The samples they collect and are sent to the laboratory for testing and checks. From this information a professional written, soil survey report is provided which gives vital information to the structural engineer to know how far the piles need to go down into the earth, to support the house structure. This is vital so your home is not only safe, but will not suffer from subsidence or any form of structural issues. Bangkok Builder has helped many people wishing to build a house with soil test surveys. If you would like us to assist you with this, please ask us. It should be done, preferably early on in the architectural phase, so the engineer has the information to finalise his structural drawings. Please contact Bangkok Builder for a soil test survey.

This home our client also asked our English speaking Thai architect to do all the architectural drawings. Once completed after some months working closely with the client, they then applied for permissions to build and we provided the price to build. An agreed start date given and then contracts were signed.

Thailand Construction Costs: How much does it cost to build a house ?

We often get asked how much does it cost to build a house in Thailand, or what are the construction costs in Thailand ? So we will try to offer some insight into what to expect and how to do it correctly.

A professional construction person if genuine, would not give you simply a figure without informing you, that construction costs vary according to the individual project, who is building it, the location and what they provide within their quotation. It is impossible to know accurate construction costs until you have finished architectural drawings, have knowledge of the specifications, size, site conditions, location and what materials are being used. Each house is different, as the architects drawings are different, the materials are different, location and site conditions could be different. Costs are calculated once all architects drawings are completed. A cost quotation can take 2-4 weeks depending on the size of house.

To know costs, the builder has to know from the architects drawings facts such as: what type of materials, product and manufacturer of each material and every aspect of the construction. This includes, windows, roof tiles, doors, electrical systems, sockets, light switches, insulation, wall material, pumps, bathroom finishes, tiles, floor coverings, light fittings, wood, steel, concrete, cement and all the other materials used within the construction. What size, what quantity, what product etc ? They need to know the details and information, then calculate quantities and amounts required to complete the construction. It is the only accurate way to know the construction cost. So to answer how much a house costs to build in Thailand, is a very difficult question to answer, as you can see, it varies according to each project.

What Bangkok Builder does, if our architect is designing the home, is to provide an approximate projected, construction cost, when our architect provides the architectural job description and fee proposal for architecture. It cannot be 100% accurate, as it will change during the design development stage and also we have no knowledge of the materials or specifications yet. But we try to give you an approximate projected guide. It is no guarantee of cost at all and is helpful information based on the architects experience in construction costs. But it gives you some idea for a starting point.

To do construction correctly and follow the correct process, you must work with the architect and have your architectural drawings completed first, before knowing accurate costs to build the house. You can discuss budgets with them and they can try their best to design a home within your budgets. But do remember that any changes or requests you make, during the architectural stage, alter that projected cost. So it is always a good idea if you are on a restrictive budget, to let the architect know in advance.

Approximate Information of House Construction Costs in Thailand: Remember construction costs can increase over time and because of market forces. But as of this date in 2018, we have seen the construction cost for houses in Bangkok to be any where from 25,000 baht per sq.m to 40,000 baht per sq.m, depending on everything we have mentioned in this article. It can be more if the house is high spec and a high end luxury house. But for a good, standard home in Bangkok and Thailand’s mainland provinces, maybe 25,000 to 35,000 baht per sq.m. Can it be less, yes of course. We have seen costs be as low as 20,000 Baht per sq.m for low end, small homes with lower specifications and material standards. Then again we have seen them be a lot higher if you are building on the islands of Koh Samui, or Phuket. As all materials have to be transported to the location. It is not usual to see construction costs of a luxury home on Koh Samui being 50,000 Baht per sq.m or more, for a full fit out. But as we say, it is important to understand that no one can know without a professional cost being done once all architectural drawings are completed.

This is not a cost quotation from us, as we do not have the required information yet, but it is merely a guide to be helpful to give you an approximate idea. But the only true way to know, is have your architectural drawings completed, all specifications and materials known. Then a professional cost quotation done by the construction contractor. It is too misleading to try and guess it without all of that accurate information.

If you would like Bangkok Builder to help you with construction costs, then please contact us. We do our best to help you restrict the costs as much as we can. But remember the only true way to know the cost of your house to build, is to have finished architects drawings. So it is best to start there and talk with our architect so we know what your expectations are and your approximate budget. Our advice is always follow the correct procedure, talk to our architect, talk to us and we can help you understand it more clearly. Do it correctly and you can have your house built to what you can afford, to a good standard. We are always happy to help and offer our best suggestions.

The Importance of an Anti Termite System Under Your House in Thailand

Termites are a tiny insect that used to be called in English,  ‘wood ants’ or ‘white ants’. Do not underestimate them. They can be a severe problem in many parts of the world and Thailand is no exception. They can cause terrible damage to your house and cause you costly repairs.

They are capable of causing serious problems to the strength and safety of an infested structure. Damage by termites can in some circumstances, render structures uninhabitable without costly repairs being carried out. They also cause terrible damage and destroy all sorts of wooden made furniture and installations.

Houses constructed mainly of wood are not the only structures threatened by termite activity. Homes constructed from other types of materials can also host termite infestations, because they are capable of getting over plaster, metal sides and more. Termites will feed on wardrobes, cabinets, floors, tables, chairs, ceilings, doors, windows, kitchen units,  and wooden furniture within  your home. You can be shocked at how quickly they can destroy things.

So it is very important to have a ‘under house’ termite system installed, at the very early stages of construction. The system is fairly simple and a series of pipes that run under your home. The piping system in conjunction with the chemicals put through them, will provide a termite barrier around the foundations of the house. They are not 100% guaranteed full proof, as there are a variety of types of termites, but anyone building a house in Thailand, should have one. They are one of the best forms of protection against termites. There are plenty of pest control companies in Thailand who can provide the service. Using careful control of the chemical application, the pipe system helps to protect against invasion by termites. The pest control company will then advise how often they need to come and release the chemicals. Often it can be only every 3 to 6 months, but do seek the advice of the company.They may also advise spraying around the home too, but do seek the professional advice of the pest control company.

Bangkok Builder always recommends it and if our architect is doing the architectural drawings, advise you to have one. If you are working with an architect of your own, we recommend you instruct them to have one in the drawings. Don’t be a victim of termites.